How To Move Time Between Phases

When time has been recorded to the incorrect phase, you can do a bulk or batch process to move them to the correct phase. Here is how.

  1. Navigate to the Project Time tab
  2. Click the move time button (adjacent to the edit button in the phase panel)
  3. Select the from and to phases
  4. Select the time slips
  5. Click the Move Time Slips button